HS2 over budget and behind schedule after government underestimate its complexity and risk

The National Audit Office (NAO) has released a critical report finding that the High Speed Two railway is over budget and behind schedule because the Department for Transport (DfT), HS2 Ltd and wider government have underestimated its complexity and risk.

DfT’s latest estimate of the cost of HS2 is between £65 billion and £88 billion (2015 prices), between 17% and 58% over available funding. The programme is still at an early stage, and costs are uncertain and could change. Full services on the entire network are now forecast to start between 2036 and 2040, between three and seven years later than originally planned.

NAO indicated that the target opening date for Phase One (London to West Midlands) was ambitious and set by comparison with other infrastructure programmes, but that DfT did not sufficiently consider that HS2 is a much larger and more challenging programme to deliver.

DfT, which is responsible for funding and overseeing delivery of the railway, set the available funding for Phase One in 2015, based on a basic design produced in 2013. Since then, forecast costs have increased on all parts of Phase One except the purchase of new trains. DfT and HS2 Ltd now estimate Phase One to cost between £31 billion and £40 billion, £3.9 billion to £12.9 billion more than its available funding.

NAO said that HS2 Ltd did not account for the level of uncertainty and risk in the programme when estimating the costs of Phase One in April 2017. It used a method for calculating contingency that was not appropriate for a programme at such an early stage of development. The £7 billion of contingency was not enough to address the significant cost increases that emerged.

The office made further criticism, saying that by not fully and openly recognising the programme’s risks from the outset, DfT and HS2 Ltd have not adequately managed risks to taxpayer money.

Phase Two of the programme is at a much earlier stage than Phase One but is already forecast to cost more than its available funding and take longer than expected. HS2 Ltd’s current forecast for when passenger services would run on Phase 2a (West Midlands to Crewe) is between 2030 and 2031, and for Phase 2b (Crewe to Manchester and West Midlands to Leeds) is between 2036 and 2040, three to seven years later than planned.

DfT estimates that costs for Phase 2a could be £6.5 billion (87% higher than the available funding) and Phase 2b £41 billion (63% higher than the available funding).

Gareth Davies, head of the NAO, said: “There are important lessons to be learned from HS2, not only for the Department for Transport and HS2 Ltd, but for other major infrastructure programmes. To ensure public trust, the Department and HS2 Ltd must be transparent and provide realistic assessments of costs and completion dates as the programme develops, recognising the many risks to the successful delivery of the railway that remain.”

A message from the Editor:

Thank you for reading this story on our news site - please take a moment to read this important message:

As you know, our aim is to bring you, the reader, an editorially led news site and magazine but journalism costs money and we rely on advertising, print and digital revenues to help to support them.

With the Covid-19 lockdown having a major impact on our industry as a whole, the advertising revenues we normally receive, which helps us cover the cost of our journalists and this website, have been drastically affected.

As such we need your help. If you can support our news sites/magazines with either a small donation of even £1, or a subscription to our magazine, which costs just £31.50 per year, (inc p&P and mailed direct to your door) your generosity will help us weather the storm and continue in our quest to deliver quality journalism.

As a subscriber, you will have unlimited access to our web site and magazine. You'll also be offered VIP invitations to our events, preferential rates to all our awards and get access to exclusive newsletters and content.

Just click here to subscribe and in the meantime may I wish you the very best.




Latest news

Barnsley College opens new digital innovation hub

Barnsley College’s newly created digital innovation hub has welcomed its first students this week. The new SciTech Digital Innovation Hub is supported The Department of...

Sheffield’s Heart of the City II scheme moves forward

Sheffield’s Heart of the City II continues to move forward with work at Leah’s Yard getting underway. Local construction firm, RF Joinery, has begun essential...

Double director appointment for Town Centre Securities

Town Centre Securities (TCS) has made two key senior appointments in its property team. The Leeds-based property investor and car parking operator has promoted Helen...

York hotel plan gets go-ahead

A new hotel is to be built on Micklegate in York, after planning approval was granted by just one vote. The 62 bedroom hotel, with...

Hull’s Whitefriargate secures £1.75m grant from Historic England

Whitefriargate in Hull has received a grant of £1.75m from Historic England. Hull City Council was informed earlier this year that its funding bid, for...

Facelift planned for prominent Sheffield building

A planning application proposing a significant facelift to Sheffield's Gaumont building, located on the junction between Barker’s Pool and Burgess Street in the city...

Related news

Barnsley College opens new digital innovation hub

Barnsley College’s newly created digital innovation hub has welcomed its first students this week. The new SciTech Digital Innovation Hub is supported The Department of...

Sheffield’s Heart of the City II scheme moves forward

Sheffield’s Heart of the City II continues to move forward with work at Leah’s Yard getting underway. Local construction firm, RF Joinery, has begun essential...

Double director appointment for Town Centre Securities

Town Centre Securities (TCS) has made two key senior appointments in its property team. The Leeds-based property investor and car parking operator has promoted Helen...

York hotel plan gets go-ahead

A new hotel is to be built on Micklegate in York, after planning approval was granted by just one vote. The 62 bedroom hotel, with...

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close