Yorkshire’s construction industry hit hard by materials shortage

The impact of building materials running short in the UK is certainly being felt in Yorkshire, where prices have soared for a wide range of common materials in recent months, according to Gent Visick’s (GV) building consultancy division.

The company’s figures reveal that steel prices in the region have risen by an average of 20% since January and timber has soared by 30%.

GV’s building consultancy division provides cost consultancy, contract administration and project management services on a wide range of new build and refurbishment projects throughout Yorkshire and beyond.

The company is also currently advising on several large-scale developments including more than 1m sq ft of new industrial space at two sites in Thirsk and Doncaster.

Gavin Ritchie, director of GV’s building consultancy division, said: “The current levels of demand for construction materials in the UK is having a big impact in Yorkshire. We’re currently seeing major shortages of common products including cold rolled steel, cement, chipboard and cladding.

“Part of the problem is that lots of construction projects have started at the same time, as the country emerged from lockdown, and the high numbers of people doing home improvements has also been well-publicised.

“This has all created a huge surge in demand and to make matters worse, the pandemic has pushed up shipping costs.

“As a result, timber prices have significantly increased, and steel prices are already up by a fifth since the start of the year and we predict they could increase by another 20% by October.

“These price increases and delays securing products are now impacting on the timings of projects. Plus, contractors are struggling to fix tender prices because in some cases prices for materials are changing each day.

“This also means actual build costs have frequently increased dramatically from when estimates and initial appraisals were carried out, which can often be 12 months before work starts.

“Depending on how contracts are worded, contractors are often having to take the hit for these price increases and delays, which puts them under additional financial pressure at an already difficult time. It’s a challenging situation, which is likely to continue until supply catches up with demand.”

A message from the Editor:

Thank you for reading this story on our news site - please take a moment to read this important message:

As you know, our aim is to bring you, the reader, an editorially led news site and magazine but journalism costs money and we rely on advertising, print and digital revenues to help to support them.

With the Covid-19 pandemichaving a major impact on our industry as a whole, the advertising revenues we normally receive, which helps us cover the cost of our journalists and this website, have been drastically affected.

As such we need your help. If you can support our news sites/magazines with either a small donation of even £1, or a subscription to our magazine, which costs just £31.50 per year, (inc p&P and mailed direct to your door) your generosity will help us weather the storm and continue in our quest to deliver quality journalism.

As a subscriber, you will have unlimited access to our web site and magazine. You'll also be offered VIP invitations to our events, preferential rates to all our awards and get access to exclusive newsletters and content.

Just click here to subscribe and in the meantime may I wish you the very best.




Latest news

Related news

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close